Planning a new off-mains drainage system

Choose the discharge route before the product. The land, regulator and design constraints come first.

The short answer

First investigate connection to the public foul sewer. If off-mains drainage is justified, assess flows, site levels, soil, groundwater, receptors and access before choosing a system. Obtain the relevant environmental authorisation, planning and building-control approvals, then commission and document the installation.

When this guide fits

Clues worth recording

  • A new home, conversion or extension is planned
  • Occupancy or daily flow will increase
  • The discharge point will move or change type
  • An existing system cannot serve the proposal
01

Start with mains feasibility

Regulators and planning policy prefer connection to public foul drainage where reasonable or practicable. Obtain evidence from the sewerage provider rather than assuming distance alone rules it out.

02

Survey the site

A designer needs intended occupancy and flows, levels, boundaries, access, soil and groundwater evidence, watercourses, wells, boreholes, flood risk, protected areas and space for maintenance or replacement.

  • Topographical and drainage survey
  • Ground investigation and percolation evidence
  • Mains connection enquiry
  • Environmental constraint check
  • Access and ownership review
03

Select and authorise the route

The choice may be septic tank to drainage field, package plant to ground or permitted surface-water outlet, or a sealed cesspit where accepted. Each has siting and operational constraints. Changes after approval should be checked again.

04

Install, commission and hand over

Use competent installers, protect the field from trafficking, commission mechanical and electrical equipment, and provide the operator with drawings, manuals, approval records, service schedule and emergency contacts.

Do not buy a tank before the discharge route, capacity and approvals have been established.

Not sure what applies to your system?Describe the trigger. We’ll help shape the next question.
Get help

Questions homeowners ask

What people usually want to know

Do I need planning permission for a septic tank?

Planning and building-control requirements depend on the work and location. Environmental authorisation is separate; check all three routes before installation.

Can roof water enter the septic system?

It should not. Clean surface water can hydraulically overload foul treatment and drainage fields and should have a separate lawful route.

Does changing an outlet create a new discharge?

In England, changing between ground and surface water or moving the discharge beyond specified limits can make it a new discharge. Check the current official criteria.

Sources & review

Evidence behind this guide

Reviewed 1 September 2026. We use primary guidance where available and label trade-body advice clearly.